St Jude’s Full Opening Now Expected in 2027, With No Confirmed Date

Must Read

One year after the rebuilt St Jude Hospital was handed over to the Ministry of Health, Saint Lucians face a further wait for its full opening, with Health Minister Moses Jn Baptiste now anticipating completion of the transition in 2027.

Speaking at Monday’s pre-Cabinet press briefing on November 16, the minister acknowledged that safety checks, system verification and adjustments had taken longer than expected. He could not give a firm date for transferring all hospital services from the George Odlum Stadium to the 100-bed facility at Augier.

“We do not have an exact timeline. I can’t tell you it is two weeks or three weeks,” Jn Baptiste said.

“We are convinced that within a reasonable time in 2027, next year, we will completely transition the hospital.”

That projection extends beyond an earlier government expectation. In April, the Ministry of Health publicly anticipated full commissioning within three to four months—a timeframe that has since passed.

The anniversary also brings renewed attention to the government’s assurances surrounding the November 16, 2025 handover. At that ceremony, Prime Minister Philip J. Pierre described the rebuilt hospital as “a promise fulfilled,” while the government’s announcement explained that commissioning would follow to prepare its systems, equipment and procedures for patient care.

Although the hospital is not yet fully operational, several services are already functioning at the rebuilt site.

Jn Baptiste said physiotherapy and dialysis patients are receiving treatment there, while administration and finance have relocated. Kitchen and laundry services are also operating from the facility.

“Each move allows staff to bring services into use in phases while maintaining care for patients who depend on the St. Jude Hospital,” he said.

Pressed on what was preventing the full transition, the minister maintained that construction was complete. The remaining work, he said, involved verifying systems, completing safety checks and making adjustments, some of which require imported appliances or replacement parts.

Commissioning also involves testing medical equipment, electrical systems, ventilation and information technology, alongside staff training and coordination of service transfers.

“It is very clear that the full verification, the safety checks and all of that … have taken some more time than we anticipated,” he acknowledged.

Jn Baptiste said the government was working with local and overseas professionals and would be guided by their advice on safely moving the remaining services.

“What we don’t want to do is to rush a transition that is not safe for the patients and to rush a transition that does not have full verification,” he said.

The minister acknowledged the long wait endured by residents of Vieux Fort and the wider south, thanking the doctors, nurses and support staff who have maintained services at the George Odlum Stadium since the 2009 hospital fire.

He also accused the opposition United Workers Party of applying a double standard. Jn Baptiste argued that the former administration took almost four years to move services into the Owen King EU Hospital, saying the COVID-19 pandemic ultimately forced that transition in March 2020.

For St Jude, however, Monday’s briefing produced no specific completion deadline. The minister pledged to keep the public informed as the remaining work proceeds.

“The people of the south, the people of St. Lucia deserve a fully functioning, safe hospital that they can depend on,” he said. “We will see this work through